Port Houston Strategic Plan
Houston, TX
Led Port Houston's Strategic Plan Update through facilitated process with broad stakeholder engagement, setting priorities for operational excellence, sustainability, and community impact across the Houston Ship Channel.
LNG-to-Power Mega Project
Dominican Republic
Pre–FID for a DR project with 2 CCGT plants, an LNG facility, a marine terminal, and transmission line extension. Managed technical, permitting, procurement, and contract matters, plus early works and turbine procurement.
Container Terminal Expansion
Houston, TX
Performed a MetOcean study to assist the Port of Houston Authority in the development of a new container berth, known as Wharf 8, at the location of the existing cruise terminal at the southeast corner of the Bayport Terminal.
Combined-Cycle Power Plant
Hannibal, OH
Owner's Construction and Contracts Management consultant for 485–MW combined-cycle plant (GE 7HA.02, STG, generator); overseeing demolition, EPC, gas interconnect pipeline, and switchyard packages.
Truck Route Analysis
Houston, TX
Provide stakeholder engagement and technical support to identify strategies for safe and efficient truck access to Port Houston's terminals and improve quality of life in and near port communities in the Houston area.
MetOcean Data Gathering
San Cristobal, DR
CAS Group was retained by a client to perform a one month field data collection effort deploying three ADCPs, including two Signature series units and one Eco, to gather marine conditions data for planning and analysis.
Combined-Cycle Power Plant
Salem, MA
Program Manager for $1B, 674–MW combined–cycle plant with GE turbines, switchyard expansion, gas pipeline, and LEED admin building; led EPC oversight, contracts, claims, design reviews, outreach, and permitting.
Trucking Industry Collaborative
Houston, TX
CAS Group designed and facilitated the Houston port region's Trucking Industry Collaborative, developing a roadmap and action plan for transitioning drayage operations to clean truck technologies and alternative fuels.
Coastal Flood Modeling for Port
NJ & NY
Supported a flood risk study for critical New York City infrastructure, assessing flood exposure and mitigation measures. Simulations modeled nine water levels across nine ARI events from one–year to 500–year conditions.
Industry Engagement
Houston, TX
Engaged Houston Ship Channel industries to define corporate social responsibility priorities and coordinated investment in neighboring port communities through the Anchored in Action community investment plan.
County Freight Study
Houston, TX
Supported technical analysis and plan development for the Harris County Freight Study to improve freight mobility, safety, and sustainability, with emphasis on origins and destinations, supply chains, and truck parking.
Greenfield Facility
Prince Rupert, BC
Performed a due diligence of a proposed greenfield logistics center located in Canada. The facility was to transload and package resin, agricultural, and pulp and wood products from rail to container for shipment overseas.
Mobility Study
Houston, TX
Support public and stakeholder engagement for Connecting Buffalo Bayou East study, informing trail and transit district improvements for safety, access, walkability, streetscapes, amenities, and economic opportunity.
LNG Terminal Oil Boom Containment Design, DR
In anticipation of future fuel oil deliveries, CAS Group was retained to provide engineering, and to procure and install a fast-track basis a permanently deployed oil containment boom system at the marine terminal.
Citywide Truck Route Plan
Houston, TX
Led preparation of Houston's Citywide Truck Route Plan through technical analysis and stakeholder and community input, defining strategies for safer, more efficient freight corridors and reduced neighborhood impacts.
Wave & Wake Study
New York, NY
Performed Coastal Data Acquisition with CAS Group's MetOcean equipment to monitor wave, current, and wake climate in New York Harbor; analyzed AIS vessel traffic to identify wake sources, frequency, heights, and periods.
Haz Mitigation & OMP
Houston, TX
Led outreach for Houston's Hazard Mitigation Plan Update and Emergency Management Plans, using meetings, surveys, and online review to shape strategies for hazards, resilience, and emergency preparedness.
Sustainability Action Plan
Houston, TX
Designed and facilitated stakeholder workshops for Port Houston's Sustainability Action Plan. Drafted plan, turning input into projects for air quality, climate resilience, equity, and sustainable operations.
Pipeline Scour Study
New York, NY
Completed field and numerical studies to identify mechanisms behind a scour hole in the Harlem River above the ConEd gas pipeline. Also developed preliminary design criteria for conceptual scour protection measures.
Urban Design Guidelines
Houston, TX
Led stakeholder engagement for Houston METRO's Transit Urban Design Guidelines. Supported plan development to shape design standards that improve safety, accessibility, sustainability, and rider experience across the system.
Platinum LEED Building
Salem, MA
Led program management for a 674–MW combined–cycle plant in Salem, overseeing EPC, permitting, contracts, stakeholder coordination, and construction of the gas lateral, switchyard, and LEED Platinum building.
Transload Facility
East Fairview, ND
CAS Group developed requirements for a client's frac sand facility in East Fairview, led EPC prequalification and contract negotiations, then served as Owner's Engineer through construction and automation.
Ammonia Export Site Screening
Texas
Performed a site screening for a marine terminal to export hydrogen as ammonia. Evaluated three Texas ports, developed conceptual layouts, ranked each site with a multi–factor matrix, and completed a risk assessment.
Packaging, Warehousing, and Logistics Facility, SC
Supported the development of its proposed packaging, warehousing, and logistics facility to support packaging and export of Polyethylene palettes. In addition, direct container loading was considered.
Distributed Power Solution
Permian Basin, Texas
Performed due diligence for a power provider in the Permian Basin. Reviewed about 50 oil-pad generators, visited sites and maintenance facilities, and assessed OPEX, CAPEX, records, and future maintenance costs.
Power Plant Intake Modification
San Cristobal, DR
Retained to perform a series of numerical modeling studies to assess the hydro dynamic condition at the intake and develop conceptual level alternatives to reduce the impact of sargassum on plant's operations.
NorthStar Transload Terminal
East Fairview, ND
Owner's Technical, Risk, and Contract Advisor pre–FID and during execution of 400–acre crude–to–rail facility; Truck unloading, storage tanks, rail, loading racks, pipeline, and bridge; delivered ahead of schedule and under budget.
Biomethane Landfill RNG Project, Whitesboro, TX
CAS Group was retained to develop an EPC agreement for implementation of a landfill RNG project in Texas. Supported the client during EPC contract negotiations and helped align terms with project execution needs.
Long-Range Plan
Port Houston, TX
Stakeholder Engagement Specialist supporting Port Houston's 20–year plan, covering investments in terminals, cargo, ship channel expansion, dredging, freight mobility, community relations, and environment.
Aviation FBO Acquisition
Sarasota, FL
Performed a fast-tracked technical due diligence in connection with the acquisition of a FBO. Main focus was assessing the validity of the CAPEX proposed by the seller in connection with the hangar expansion program.
Small Scale LNG Facility
Guadalajara, Mexico
Retained to participate in a series of meetings during which was presented in an Open Book Estimate for the design, procurement, and construction of a 100 MTD (234.5 cum/day) ssLNG terminal in Jalisco, Mexico.
LNG Terminal Fender Replacement, DR
Reviewed three vendor bids for a fender replacement, prepared clarification questions, expanded RFP requirements, and created evaluation criteria. Findings ranked all bids and supported an award recommendation.
LNG Terminal Port and Terminal Regulations Update, DR
Updated a marine terminal and port rules for a client, incorporating fuel oil delivery requirements, safe operating conditions, cargo transfer procedures, and LNG delivery rules. Facilitated 2 team workshops.
LNG Facility & Marine Terminal
Jacksonville, FL
Consultant for $110M+ LNG plant (120k gpd, 2M gal storage); Owner's Contracts Manager overseeing team, marine terminal design, and siting/design basis; small-scale coastal facility with truck and barge loading.
LNG Terminal Berth Upgrade
Dominican Republic
Developed concepts to strengthen LNG berth for larger carriers; mooring studies and as–built redlines; advanced detailed design, tender docs, cost, and schedule; supported QRH, berthing aids, and CM during implementation.
NorthStar Frac Sand Terminal
East Fairview, ND
Led contracts, engineering, and PM for a two-phase automated frac sand facility: railcar unloading, nine 2,500–ton silos, three truck bays, and handling systems; delivering high efficiency, safety, and reliability.
LNG Receiving Terminal
Dominican Republic
Program Manager for this LNG terminal; led siting, marine/coastal design, modeling, and MetOcean; also managed FEED, FSRU conversion, DBB terminal, LNG vaporization EPCM, and gas pipeline EPC services.
Mixed–Use Waterfront Dev
New York, NY
Coastal Engineer for East River waterfront project; led data acquisition and modeling for River Street Master Plan with open space, in-water access, esplanades, berms, breakwaters, and wetlands to boost resilience and access.
Breakwater Inspection
Australia
Inspected four coastal protection structures at Rio Tinto's Dampier terminal and assessed their overall condition and effectiveness. Findings on the causeway and revetments were summarized and submitted to Rio Tinto.
Marine Terminal and Storage Expansion, Port Arthur, TX
Retained to develop a new marine terminal at Texaco Island, Port Arthur along with incremental storage refinery. Scope included site visit, conceptual development, and preparation of pre–FEED scope of work.
LNG Terminal Second Gangway
Dominican Republic
CAS Group advised the client in the Dominican Republic, to assess the facility, oversee studies for a second tank and fourth regasification train, and support EPC oversight for a gas line for the terminal.
Aviation Hangar
Chicago, IL
Performed technical due diligence for a proposed airport hangar expansion. Oversaw an independent Class 5 estimate, drafted the EPC contract, and supported negotiations for project implementation of the hangar.
Due Diligence of Compressed Natural Gas Station, FL
Performed a targeted Phase 1 Due Diligence effort of a Compressed Natural Gas (CNG) fueling stations. Scope included a site visit, review of O&M records and costs, SOPs, and a technical assessment of the facilities.
Methyl Methacrylate Loading Barge Terminal, AR
The development concept for proposed Chemical Terminal involves barging methyl methacrylate to a new receiving and storage terminal. Consisted of a new barge dock and a storage and distribution terminal.
Power Plant Study
Vlore, Albania
Assessed condition and readiness of 100MW CCGT plant for fuel conversion and restart. Includes reactivation cost and schedule analysis, concept for an alternative heat rejection system, and expansion pre–feasibility.
LNG Terminal Fuel Oil Tankers Compatibility Study, DR
Inspected a 100MW CCGT plant to assess condition and readiness for fuel conversion and restart. Included reactivation cost and schedule analysis, an alternative heat rejection concept, and expansion pre–feasibility
LNG Pipeline Surge Study
Punta Caucedo, DR
Assessed the possibility of the LNG pipeline connecting the unloading arms at terminal to the LNG storage tank could experience an overstress scenario in case of an emergency shut down event at the berth.
Micro-Steam Turbine System
International
CAS Group performed targeted Phase 1 Due Diligence of a distributed power system based on micro-steam turbines include a review of the technology and its efficiency as well as site visit to inspect pilot project.
LNG Terminal Dynamic Mooring Analysis, Dominican Republic
Performed dynamic mooring analyses for alternative mooring arrangements for different LNG carriers during implementation of berth strengthening project to establish temporary limiting environmental operating criteria.
Regional Flood Study
Lower Rio Grande Valley, TX
CAS Group provided coastal engineering, numerical modeling, technical expertise, and public engagement services for a regional flood study in the Lower Rio Grand Valley led by the Texas General Land Office (GLO).
Coastal Flood Study
Dili, East Timor
Retained to determine the base flood elevations for a U.S. State Department facility, in East Timor, by analyzing offshore wave climate, storm surge, and extreme swell, as well as wave runup along the Savu Sea coast.
LNG Marine Terminal Improvements, DR
Performed detailed design and the bid package for reinforcement of breasting and mooring dolphins, replacement of Quick Release Hooks, and repair of catwalks and trestle at LNG receiving terminal.
Transload Facility Due Diligence
St. Gabriel, MS
Performed technical due diligence for proposed oil transload facility with unit–train offloading, tank farm, dock for Aframax and barges with loading equipment, and interconnecting piping, utilities, and controls.
Mixed Use Waterfront Dev
New York, NY
Provided coastal engineering and modeling for mixed use master plan with resilient waterfront open space, flood mitigation, habitat enhancement, public access, esplanades, berms, breakwaters, marshes, and wetlands.
Marine Terminal Assessment
Wilmington, NC
CAS Group performed assessment of marine terminal including visual assessment of existing pier, trestle, and material handling equipment as well as assessment of anticipated CAPEX and OPEX requirements.
Coastal Resiliency Project
New York, NY
Provided coastal engineering, numerical modeling, community engagement, and contracts support on a PM/CM team delivering over $1 billion in coastal resiliency projects along the East River in New York City.
Proposed Marine Terminal
Port Arthur, TX
Advisory services for Phase 1 due diligence of a proposed marine terminal, with pre–FID planning also evaluated. Continued oversight and technical review services helped the sponsor advance development decisions.
Gas Pipeline
Dominican Republic
Served as technical advisor monitoring construction of the 50 km, 24–inch diameter Eastern Pipeline linking San Pedro de Macorís power plants to the AES Andres LNG receiving terminal in the Dominican Republic.
Gansevoort Peninsula Park
New York, NY
CAS Group provided coastal numerical modeling and design for revetments, artificial beaches, living shorelines, and kayak access for the 5.65-acre Gansevoort Peninsula waterfront park development on the Hudson River.
LNG-to-Power Project
Acajutla, El Salvador
CAS Group supported due diligence for a potential greenfield LNG-to-power acquisition in Central America, serving as technical expert and participating in meetings with the development company's management.
LNG Plant Due Diligence
Brownsville, TX
Supported due diligence for a proposed LNG plant on the Texas coast, serving as technical expert in meetings with management, consultants, and EPC contractors while reviewing siting documents and compliance.
LNG Terminal Due Diligence
Brownsville, TX
Provided technical due diligence for a proposed LNG terminal. Services included reviewing siting, MetOcean, geotechnical, logistics, flooding, coastal protection, EPC contract and FEED agreements, and key project risks.
Marine Terminal Conversion
Port Arthur, TX
Technical advisor on conversion of POPA's Berth 3 from general cargo to liquid fuel loading, including quick release hooks, loading arms, control systems, and pipelines connecting tank farms to the berth.
Analysis of Oil Terminal
Tacoma, WA
CAS Group performed the preliminary analysis and logistics simulations to estimate optimal storage capacity for a proposed crude-by-rail facility at the Port of Tacoma and develop conceptual layouts for facility.
Marine Terminal Upgrades
Port Arthur, TX
Performed condition assessment of a liquid bulk storage and export facilities in Port Lavaca, and then provided engineering and project management for storage and marine facility upgrades and expansion.
Hudson River Waterfront Park
New York, NY
Coastal engineer for numerical modeling and design of revetments, artificial beaches, living shorelines, and kayak facilities for a new 5.65-acre Hudson River waterfront park with sandy beach, salt marsh, and habitat enhancements.
Citywide Coastal Resiliency
New York, NY
Coastal engineering, numerical modeling, community engagement, and contracts specialists on a PM/CM team implementing coastal resiliency, reducing flood risk from storms and sea level rise while improving waterfront access.
Value Engineering
US Army Corps of Engineers
Coastal and marine engineering SME providing value engineering services to the USACE Vicksburg District across all project phases — flood protection, navigation, environmental restoration, dredging, and urban infrastructure.
LNG Terminal Expansion
Dominican Republic
Owner's technical and strategic advisor for LNG terminal development studies covering optimal tank sizing, condition surveys, siting, debottlenecking, and FEED; including a new tank, vaporizers, and truck loading facilities.
LNG Terminals Due Diligence
Gulf of Mexico
Lead technical advisor for due diligence of conventional and floating LNG liquefaction facilities, covering fatal flaw analysis, CAPEX/OPEX validation, schedule, risk, constructability, and project management assessments.
LNG to Power Due Diligence
The Americas
Lead technical advisor for greenfield LNG–to–Power due diligence, assessing FSRU terminal feasibility, subsea pipeline, power plant constructability, CAPEX/OPEX, EPC agreements, risk, and independent operability forecast.
Eastern Pipeline
Dominican Republic
PM/CM advisory for a 50km, 24–inch natural gas pipeline from an LNG terminal to multiple power plants in the Dominican Republic, addressing technical, contractual, and schedule challenges while monitoring project progress.
Community Visioning Process
New York, NY
Public Engagement Specialist for NYCHA visioning at three developments; provided meeting design, outreach support, facilitator training, and input integration into plans. Over 900 participants shaped a safe, clean, connected vision.
Post-Disaster Recovery Plan
Nassau County, NY
Public Engagement Specialist for five Long Island communities hit by Hurricane Sandy. Supported rebuilding for residents, businesses, and infrastructure; designed engagement events, trained facilitators, and drafted plans.
Post-Disaster Recovery Plan
Nashville, TN
Public Engagement and Housing Specialist for recovery after flooding event. Worked with community and metro–government to identify projects for stronger neighborhoods, disaster–resistant infrastructure, housing, and resilience.
Land Use Assessment
Unalaska, AK
Ports and marine SME for the APA's Community Planning Assistance Team, guiding Unalaska's land use plan for industrial expansion at Port of Dutch Harbor, the top US fishing port and oil exploration staging area.